A new cost now applies to residential development in England. The Building Safety Levy came into operation on 1 October 2026, and it is charged on most new residential schemes of ten or more homes. The money raised will help pay for fixing building safety defects, such as unsafe cladding, across England. For developers, it adds a new line to every appraisal. For contractors and subcontractors, it is one more pressure on the viability of the schemes they rely on for work.
Disclaimer: This article is for general information only and reflects the Building Safety Levy (England) Regulations 2025 and government guidance available at the time of writing in October 2026. Whether a particular development is chargeable, and how much is due, depends on detailed rules in the regulations. Levy rates in the worked examples are illustrative. Always check the official rates table for your local authority and take specific advice on your scheme.
What the Building Safety Levy Is
The Building Safety Act 2022 gave the government power to introduce a levy on new residential buildings in England that require certain building control approvals, to raise money for building safety. After a one year delay, the levy started on 1 October 2026. The government expects it to raise around £3.4 billion over ten years.
The levy applies in England only. It is collected by local authorities with building control responsibilities, which act as levy collecting authorities and pass the money to central government.
Which Developments Are Caught
The levy applies to developments that create new residential floorspace and form, or are part of, what the regulations call a major residential development. That means at least ten new dwellings, or at least thirty bedspaces in purpose built student accommodation. Purpose built student accommodation, build to rent schemes and retirement homes are within scope.
A range of developments are exempt. These include affordable housing, non social homes built by not for profit registered providers, NHS hospitals, care homes, supported housing, children's homes, domestic abuse shelters, military accommodation and criminal justice accommodation, as well as developments of fewer than ten units.
The words "or is part of" matter. A larger scheme split into smaller phases or applications may still be treated as a single major residential development. Developers should not assume that dividing a site into batches of nine homes will avoid the levy.
How the Levy Is Calculated
The levy is charged per square metre of chargeable floorspace in a development. Each local authority has its own rate, set using average house prices in that area. So the highest rates are in the most expensive areas and the lowest rates in the cheapest.
Kensington and Chelsea has the highest rate, at £100.35 per square metre, and County Durham the lowest, at £12.70. Developments on previously developed land, often called brownfield sites, pay 50% of the standard rate for their area. Rates are due to be reviewed every three years.
The full rates for every local authority are published in the government's Building Safety Levy guidance. For developers in Hertfordshire, North London and the surrounding areas, it is worth checking the specific rate for each local authority where you are active, because rates can differ significantly between neighbouring boroughs and districts.
When the Levy Applies and How It Is Collected
The levy applies to relevant building control applications and notices submitted on or after 1 October 2026. It does not apply to applications submitted before that date. Even if an existing application is later varied after 1 October 2026, for example through an amendment notice or a further full plans application for the same works, the levy still does not apply.
Developers must provide levy information as part of their building control application. If they do not, the application can be rejected. Further information is collected at the commencement notice stage, and the levy is then calculated by the collecting authority.
The levy must be paid before the works are completed. The government has rejected calls for staged payments on phased developments, citing the administrative burden on collecting authorities. If the levy is not paid, the building control authority will withhold the completion certificate or reject the final certificate. In practice, that can delay sales, handovers and the release of development finance.
Worked Examples
The rates used in these examples are illustrative only. Always check the official rate for your local authority.
Worked Example 1: A Brownfield Apartment Scheme
Larchwood Homes Ltd is building fourteen apartments on a former industrial site in an outer London borough. The scheme has 1,100 square metres of chargeable floorspace. For illustration, assume the borough's standard levy rate is £60 per square metre. Because the site is previously developed land, the 50% discount applies, giving a rate of £30 per square metre.
The levy is 1,100 square metres multiplied by £30, which comes to £33,000, or roughly £2,360 per apartment. On a greenfield site in the same borough, the levy would have been £66,000. The levy must be paid before Larchwood Homes receives its completion certificate, so it needs to be built into the development cash flow forecast, not just the overall appraisal.
Worked Example 2: A Small Scheme Below the Threshold
Brookfield Developments Ltd is building nine houses on a single plot, with no connection to any other development. Because the scheme provides fewer than ten dwellings, it is not a major residential development and no levy is payable.
If Brookfield also owned the adjoining land and planned to build a further six houses there as part of the same overall project, the position could be different. The two phases might together be treated as a single major residential development of fifteen homes, bringing both within the levy. Brookfield should take advice before relying on the small site exemption.
Worked Example 3: Timing of the Building Control Application
Two developers, each planning a twenty home scheme in the same district, submitted their building control applications a few days apart. The first submitted a full plans application on 25 September 2026, before the levy started, so no levy applies to that scheme, even if the plans are amended later. The second submitted on 5 October 2026, so the levy applies to the whole development. The difference in cost could easily run into tens of thousands of pounds, which shows how important the application date can be when appraising and comparing sites.
Accounting and Tax Treatment
For developers who build homes to sell, the levy is a cost of developing the properties. Under FRS 102, it would normally be included in the cost of the development as work in progress or stock, alongside land, construction and professional fees. It then reaches the profit and loss account as part of cost of sales when the homes are sold. For Corporation Tax, the timing of the deduction generally follows that accounting treatment. This means the cash is paid before completion, but the tax deduction is spread over the sales.
For investors building homes to hold and let, such as build to rent schemes, the levy is likely to form part of the capital cost of the building. It will not be deductible against rental income, but should form part of the base cost when the property is eventually sold. Capital allowances such as the Structures and Buildings Allowance do not generally apply to residential dwellings.
Because the levy is paid early in the life of a development but relieved later, it adds to the funding requirement. Lenders will want to see it reflected in appraisals and drawdown schedules, so build it into your figures from the start.
What It Means for Contractors and Subcontractors
The levy is paid by the developer, not by the contractors or subcontractors who build the homes. However, it adds to the pressure on scheme viability at a time when developers are also facing higher borrowing costs and, potentially, a contribution to the new Your First Home equity loan scheme. For subcontractors, that can mean tighter pricing, delayed starts or schemes that do not go ahead.
On the positive side, the levy is intended to fund building safety remediation, and the expected boost to demand from Your First Home could increase new starts. Either way, keeping a close eye on cash flow, payment terms and CIS deductions remains essential. Our guide to CIS explains how deductions and refunds work.
Practical Steps for Developers
Check the official levy rate for every local authority where you have schemes in the pipeline, and confirm whether each site counts as previously developed land.
Update development appraisals for schemes with building control applications submitted on or after 1 October 2026, and build the payment into the cash flow forecast before completion.
Review whether any phased or adjoining sites could be treated as a single major residential development.
Make sure levy information is included in building control applications to avoid rejection.
Talk to your lender early about how the levy will be funded within the facility.
Frequently Asked Questions
When did the Building Safety Levy start?
It came into operation on 1 October 2026 and applies to relevant building control applications and notices submitted on or after that date.
Who pays the Building Safety Levy?
The developer pays. It is collected by the local authority with building control responsibility for the area and passed to central government to fund building safety work.
Does the levy apply to small developments?
Developments of fewer than ten dwellings, or fewer than thirty bedspaces of purpose built student accommodation, are generally outside the levy. However, a small phase that is part of a larger development may still be caught.
How much is the Building Safety Levy?
It is charged per square metre of chargeable floorspace, at a rate that varies by local authority. Rates range from £12.70 per square metre in County Durham to £100.35 in Kensington and Chelsea, with a 50% discount for previously developed land.
Is affordable housing exempt?
Yes. Affordable housing is exempt, along with a range of other uses, including supported housing, care homes, NHS hospitals and certain homes built by not for profit registered providers.
What happens if the levy is not paid?
The building control authority will withhold the completion certificate or reject the final certificate, which can delay the sale or occupation of the homes.
Can the levy be paid in stages on a phased development?
No. The government has said it does not intend to allow staged or phased payments.
Is the levy deductible for tax?
For developers building homes to sell, it is generally treated as part of the cost of the development and relieved for tax as the homes are sold. For investors building homes to let, it is likely to be a capital cost. Your accountant can confirm the treatment for your circumstances.
What CoreAcc Accountants Can Help You With
CoreAcc Accountants works with developers, housebuilders, contractors and subcontractors across Hertfordshire, North London and the surrounding areas. We can help you build the Building Safety Levy into development appraisals and cash flow forecasts, account for it correctly within work in progress and stock, and model its combined effect alongside higher borrowing costs and the developer contribution expected under Your First Home. For subcontractors, we manage CIS, cash flow and the financial reporting that lenders and main contractors increasingly ask for.
Get in Touch
If you have residential schemes in the pipeline, or you are appraising new sites, contact CoreAcc Accountants. We will help you understand what the Building Safety Levy means for each scheme and make sure it is reflected properly in your numbers.
CoreAcc Accountants is an ACCA accredited firm of Chartered Certified Accountants based in Borehamwood, Hertfordshire. This article was published in October 2026 and reflects the Building Safety Levy regulations and government guidance available at the time of writing. Levy rates in worked examples are illustrative. It does not constitute professional or legal advice. Always seek specific advice tailored to your individual circumstances.